Title: Authorization to close project Woodcreek II Improvements and return the $40,000.00 of the 2018 General Obligation Bond funds to the appropriate basin. Original Agenda Item Number 23-1366
Attachments: 1. Signed Close out Woodcreek II
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 02-23-26

 

Title:

title

Authorization to close project Woodcreek II Improvements and return the $40,000.00 of the 2018 General Obligation Bond funds to the appropriate basin. Original Agenda Item Number 23-1366

End

 

Background:

The project in Woodcreek II Subdivision was to Design a mitigation plan to address ground water seeping through driveways and sidewalks in the Woodcreek II Subdivision. $40,000.00 was authorized by council for these repairs. Non-Responsiveness from the property owners involved in this project has resulted in the project being closed. 

 

Cost:                                                                $0.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Project Close Out Form 

 

Recommendation:

recommend

Authorize the closing of the project Woodcreek II Improvements and return the $40,000.00 of the 2018 General Obligation funds to the appropriate Basin. Original Agenda Item number 23-1366

end