Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 24-999    Name:
Type: Consent Item Status: Agenda Ready
File created: 7/23/2024 In control: Drainage Advisory Committee
On agenda: 7/29/2024 Final action:
Title: Approval of and recommendation of Final Acceptance of the Drainage Advisory Committee project Eagle Creek, original Agenda Item Number 20-1054
Attachments: 1. Complete_with_Docusign_Close_out_-_Eagle_Cre
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 07/29/24

 

Title:

title

Approval of and recommendation of Final Acceptance of the Drainage Advisory Committee project Eagle Creek, original Agenda Item Number 20-1054

End

 

Background:

The project in Eagle Creek Subdivision was to install an inlet in the road and a storm sewer system to drain the runoff to the detention pond. The project was designed in 2022 and was bid in January 2023. The final pay app was paid in May 2024. The project was inspected during the rain events in late April and early May. The new storm sewer system is mitigating the issue of drainage into citizen’s homes. The stormwater division is asking that $2,124.24 be moved back into the Adams Creek Basin fund.

 

Cost:                                                                $0.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Project Close Out Form 

 

Recommendation:

recommend

Approval of and recommendation of Final Acceptance of the Drainage Advisory Committee project Eagle Creek, original Agenda Item number 20-1054.

end