Broken Arrow City Council
Meeting of: 11-01-16
To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Acceptance of a Utility Easement and Temporary Construction Easement for a tract of land that is part of Lots Ten (10) and Eleven (11), Block One (1), East Haskell Addition, an addition to the City of Broken Arrow, Tulsa County, State of Oklahoma, according to the recorded plat thereof for the 9th Street Widening from Elgin to El Paso (Project No. ST1210)
End
Background:
The attached Utility Easement and Temporary Construction Easement conveyed to the City of Broken Arrow from Kenneth Lewis McBroom and Sandra Mae McBroom, husband and wife.
Payment for the Temporary Construction Easement includes a temporary construction easement over the Permanent Utility Easement of 700 sf.
Staff has reviewed this action and recommends approval.
Funding for this project is from 2011 General Obligation Bond Issue.
Cost: Permanent Utility Easement: 700 SF @ $3.00/SF X 75% = $1,575
Temporary Construction Easement: 700 SF @ $3.00/SF X 25%= $525
Damages: $4,000.00
Total Compensation Amount (Rounded): $ 6,100.00
Prepared By: Alex M. Mills, P.E., Director of Engineering and Construction
Reviewed By: Finance Department
Assistant City Manager-Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: Utility Easement
Temporary Construction Easement
Recommendation: Accept the Utility and Temporary Construction Easements.