Approval and authorization of Final Acceptance for the public improvement at KCL Commerce Crossing, located at 3925 West Albany Street
End
Background:
Lithko Contracting, LLC has completed the construction for KCL Commerce Crossing. The required improvement is in accordance with approved construction plans and appropriate construction documents. This improvement has been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvement is the following: (1) Paving, (Sidewalk and Approaches).
The owner desires to donate the public improvement identified above to the City. This improvement has an approximate value of $10,999.78.
Cost: $0
Prepared By: Alex Mills, P.E., Engineering and Construction Director
Reviewed By: Engineering and Construction Department
Finance Department
Assistant City Manager-Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: Detailed Assessment Breakdown
Recommendation:
Approve Final Acceptance and Donation of the Public Improvement: Paving, (Approaches and Sidewalk).