LEGISLATIVE RESEARCH CENTER
File #: 24-1232    Name:
Type: General Business Status: Agenda Ready
File created: 9/9/2024 In control: Broken Arrow City Council
On agenda: 9/17/2024 Final action:
Title: Consideration, discussion, and possible award of the lowest responsible bid to Cherokee Pride Construction, Inc., and approval and authorization to execute a construction contract for the Arrow Forge - Innovation District Improvements (Project No. 2352100)
Attachments: 1. 2352100 - Arrow Forge Bid Tab

Broken Arrow City Council

Meeting of: 09-17-2024

 

Title:

title

Consideration, discussion, and possible award of the lowest responsible bid to Cherokee Pride Construction, Inc., and approval and authorization to execute a construction contract for the Arrow Forge - Innovation District Improvements (Project No. 2352100)

End

 

Background:

On March 21, 2023, Broken Arrow City Council approved and authorized the Engineering firm, BKL, Inc., to design roadway, stormwater, gravity sanitary sewer, and water for Arrow Forge, located south of Florence Street between Olive Avenue and Aspen Avenue.  Arrow Forge includes 4,700 feet of asphalt roadway, 960 feet of sidewalk, 8,326 linear feet of curb and gutter, 2,509 linear feet of storm sewer and associated appurtenances, 6,720 feet of waterline, and 4,060 feet of gravity sewer and associated appurtenances.  

Engineering and Construction Department staff (E&C), working in conjunction with BKL, Inc., prepared final plans and documents for bidding.  The project was advertised on August 20
th and August 27th, 2024.  Six (6) bids were received and opened on September 10th, 2024.  The Certified Bid Tabulation is attached.  The lowest responsible bidder was Cherokee Pride Construction, Inc. with a total bid of $4,627,304.53.  The Engineers Estimate for the project is $7,215,176.85.

 

Cost:                                                                $4,627,304.53

Funding Source:                     2018 GO Bond, ARPA

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Certified Bid Tabulation.

 

Recommendation:

recommend

Award the lowest responsible bid to Cherokee Pride Construction, Inc., and approve and authorization execution of a construction contract for the Arrow Forge - Innovation District Improvements (Project No. 2352100)

end