Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 26-194    Name:
Type: Consent Item Status: Agenda Ready
File created: 1/20/2026 In control: Drainage Advisory Committee
On agenda: 2/23/2026 Final action:
Title: Authorization to close project Freeport and Cedar and return the $19,785.50 of the 2018 General Obligation Bond funds to the appropriate basin. Original Agenda Item Number 25-1069
Attachments: 1. Signed Close out - Freeport and Cedar
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 02-23-26

 

Title:

title

Authorization to close project Freeport and Cedar and return the $19,785.50 of the 2018 General Obligation Bond funds to the appropriate basin. Original Agenda Item Number 25-1069

End

 

Background:

The project Freeport and Cedar was to mitigate erosion and re-establish the ditch along W. Freeport St.

The work was performed by the City’s Streets and Stromwater team with a final cost of $214.50.   

 

Cost:                                                                $0.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Project Close Out Form 

 

Recommendation:

recommend

Authorize the closing of the project Freeport and Cedar and return the $19,785.50 of the 2018 General Obligation funds to the appropriate Basin. Original Agenda Item number 25-1069