File #: 24-1505    Name:
Type: Consent Item Status: Agenda Ready
File created: 11/4/2024 In control: Broken Arrow City Council
On agenda: 11/19/2024 Final action:
Title: Acceptance of the Drainage Advisory Committee's recommendation to approve expenditure of 2018 General Obligation (GO) Bond, Proposition 6 funds for construction of erosion mitigation and repair the leaking pond spillway at Shenandoah Valley at Battle Creek
Attachments: 1. 24-015 Packet
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 11/19/24

 

Title:

title

Acceptance of the Drainage Advisory Committee’s recommendation to approve expenditure of 2018 General Obligation (GO) Bond, Proposition 6 funds for construction of erosion mitigation and repair the leaking pond spillway at Shenandoah Valley at Battle Creek

End

 

Background:

The case was brought before the Drainage Advisory Committee on October 28, 2024. The Committee voted 7-0 to recommend approval of expenditure of funds.

The proposed project in Reserve A of the Shenandoah Valley at Battle Creek subdivision is to mitigate erosion and construct repairs to the leaking detention pond spillway. 

The Property Owners Association (POA) is requesting a partnership with the City to repair the leaking pond. The DAC previously approved funds for an engineering study that was completed in 2023. The POA has contracted with a private firm to complete the construction plans that were completed in September 2024.

Site investigations confirmed that the pond is leaking and eroding around the spillway and that a 10-inch sanitary sewer is directly under the spillway. This area flows to Ford Creek (Unnamed).

 

Cost:                                                                $45,000.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Report, Exhibits   

 

Recommendation:

recommend

Accept the Drainage Advisory Committee’s recommendation to approve expenditure of 2018 GO Bond, Proposition 6 funds for construction of erosion mitigation and repair the leaking pond spillway at Shenandoah Valley at Battle Creek.