Approval of and authorization to execute Change Order No. 1 with Cherokee Pride Construction, Inc. for the Bristol Ponds Stormwater Improvements (SW25080)
End
Background:
The Bristol Ponds Stormwater Improvements project is to stabilize the channel and inlet, regrade the south side of the pond, and rebuild the outlet structure.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Contract Bid Item No. 8, Type 1-A plain rip-rap, and bid item Class AA Concrete contained miscalculation that was not identified by the design engineer during the design phase. The final quantity change order reflects the actual quantities placed in the field. Temporary silt fence, temp silt dike, stabilized construction exit and dewatering were not required and therefore not utilized. Solid slab sodding was completed at a quantity less than the original contract amount.
Total time added to contract is:
- 0 Days
The total cost for Change Order #1 amounts to $112,079.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $112,079.00
Total Cost of Change Orders: $112,079.00
Original Contract Amount: $86,786.00
Revised Contract Amount: $198,865.00
Percent Change in Contract: 129.14%
Applicable to Comp. Bid Act: 0.0%
Cost: $112,079.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Change Order 1 Rip Rap
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction. INC for the Bristol Ponds Stormwater Improvements (SW25080)