Broken Arrow City Council
Meeting of: 03-03-2026
Title:
title
Approval of and authorization to execute Change Order No. 4 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)
End
Background:
The BAPSC Fire Department Annex Building project is to renovate the existing facility for the Fire Department. This project will add 7 Ambulance bays allowing for the quick resupply of all Ambulances throughout the City of Broken Arrow.
Change Order #4 addresses the following additions/deletions/changes to the contract:
- This Change Order is to amend the original contract price from $939,153.28 to include Bid Alternate 1: Exterior Wall Paint. This will change the contract price to $958,400.78
- There is a 15-day change in contract time.
The total cost for Change Order #4 amounts to $19,247.50
The additional cost associated with these changes is as follows:
Previous Change Orders: $159,586.61
This Change Order(s): $19,247.50
Total Cost of Change Orders: $178,834.11
Original Contract Amount: $958,400.78
Revised Contract Amount: $1,117,987.39
Percent Change in Contract: 19.04%
Applicable to Comp. Bid Act: 13.37%
Cost: $19,247.50
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BAPSC Fire Dept Annex Change Order 4
Recommendation:
recommend
Approve and authorize execution of Change Order #4 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building Project (191711)
end