Skip to main content
LEGISLATIVE RESEARCH CENTER
File #: 26-253    Name:
Type: Consent Item Status: Agenda Ready
File created: 2/2/2026 In control: Broken Arrow City Council
On agenda: 3/3/2026 Final action:
Title: Approval of and authorization to execute Change Order No. 4 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)
Attachments: 1. Change_Order__4_Exterior_Paint_Signed
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 03-03-2026

 

Title:

title

Approval of and authorization to execute Change Order No. 4 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building project (191711)

End

 

Background:

 The BAPSC Fire Department Annex Building project is to renovate the existing facility for the Fire Department. This project will add 7 Ambulance bays allowing for the quick resupply of all Ambulances throughout the City of Broken Arrow.  

Change Order #4 addresses the following additions/deletions/changes to the contract:

-                     This Change Order is to amend the original contract price from $939,153.28 to include Bid Alternate 1: Exterior Wall Paint. This will change the contract price to $958,400.78

 

-                     There is a 15-day change in contract time.

 

 The total cost for Change Order #4 amounts to $19,247.50

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $159,586.61

This Change Order(s):                                                               $19,247.50

Total Cost of Change Orders:                                          $178,834.11

Original Contract Amount:                                          $958,400.78

Revised Contract Amount:                                          $1,117,987.39

 

Percent Change in Contract:                                          19.04%

Applicable to Comp. Bid Act:                     13.37%

Cost:                                                                $19,247.50

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          BAPSC Fire Dept Annex Change Order 4
 

Recommendation:

recommend

Approve and authorize execution of Change Order #4 with Scissor Tail Construction LLC for the Broken Arrow Public Safety Complex Fire Department Annex Building Project (191711)

end