Approval of and authorization of Final Acceptance for the public improvement at Emerson Orthodontics located at 800 West Mission Street
End
Background:
All American Plumbing has completed the construction for Emerson Orthodontics. The required improvement is in accordance with approved construction plans and appropriate construction documents. This improvement has been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvement is the following: (1) Sanitary Sewer.
The owner desires to donate the public improvement identified above to the City. The improvement has an approximate value of $45,272.02.
Cost: $0
Funding Source: Source
Requested By: Alex Mills, P.E., Engineering and Construction Director
Approved By: Michael L. Spurgeon, City Manager
Attachments: Detailed Assessment Breakdown
Recommendation:
recommend
Approve and authorize Final Acceptance for the public improvement.