Title: Approval of and authorization to execute a Gas Facilities Relocation Agreement between Oklahoma Natural Gas Company (ONG) and the City of Broken Arrow for Omaha Street Culvert Project (Project No. SW1604)
Attachments: 1. ONG Agreement

Broken Arrow City Council

Meeting of: 07-03-2018

 

Title:

title

Approval of and authorization to execute a Gas Facilities Relocation Agreement between Oklahoma Natural Gas Company (ONG) and the City of Broken Arrow for Omaha Street Culvert Project (Project No. SW1604)

End

 

Background:

The City of Broken Arrow (COBA) plans to replace a box culvert on Omaha Street near North 30th Street. In order to accommodate the new construction, existing Oklahoma Natural Gas Company (ONG) gas facilities need to be relocated. All of these existing facilities are located within existing private ONG easements, and as such, the COBA must reimburse ONG for the full cost of relocating those facilities.

 

The total anticipated construction cost for this work is $68,142.00, of which, the COBA portion is $68,142.00 (100.00%).  The attached Agreement details this costs and serves as authorization for ONG to begin the relocation process.

 

Cost:                                                                $68,142

Funding Source:                     2014 GO Bonds

Requested By:                      Alex Mills, P.E., Director of Engineering & Construction

Approved By:                      Michael L. Spurgeon, City Manager

Attachments:                                          Agreement for Gas Relocation Facilities.

Recommendation:

recommend

Approve and authorize execution of the ONG-City of Broken Arrow Agreement for Gas Facilities Relocation for the East Omaha Street culvert replacement near North 30th Street (Project SW1604).