Title: Notification of Quarterly Enterprise Resource Planning (ERP) Systems Status Report for City Council
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 2/20/2024

Title:
title
Notification of Quarterly Enterprise Resource Planning (ERP) Systems Status Report for City Council
End

Background:
This is a quarterly Enterprise Resource Planning (ERP) systems status report for City Council. All systems are live and are in normal support mode, and the IT Department handles all day to day activity supporting each of these systems and their daily operation including needed maintenance and administration. This report will provide a summary of all of those activities from the past 90 days for all major systems.
Our systems from Tyler Technologies are requiring their first major upgrade since going live with Munis. With upgrades for ExecuTime and EnerGov complete, staff is completing the planning for an upgrade to Munis.

Below is listed the daily activity handled by the IT Department for the past 90 days. Tickets opened for support and then closed represents ongoing efforts for the system user. Any tickets still open are being actively worked and will show up as closed in the next status report.
Past 90 Days System Support Activity
Tyler Munis Financials:
31 tickets total
21 closed
10 still open

Tyler Munis Utility Biling:
2 tickets total
1 closed
1 still open

Tyler Munis Human Capital Management / ExecuTime:
15 tickets total
14 closed
1 still open

Tyler Munis Enterprise Asset Management:
0 tickets

Tyler EnerGov:
6 tickets total
5 closed
1 still open

Tyler InCode / Tyler Brazos:
18 tickets total
15 closed
3 still open

MyCivic:
1 ticket total
1 closed

HelpDesk support tickets last 4 months (121 total):
Financials:
35 tickets total
34 closed
1 still open

Utility Billing:
1 ticket total
1 closed

Human Capital Management / ExecuTime:
28 tickets total
27 closed
1 still open

Enterprise Asset Management:
35 tickets total
35 closed

EnerGov:
17 tickets total
17 closed

InCode / Brazos
5 tickets total
5 closed


Cost: $0