File #: 26-150    Name:
Type: Public Hearings Status: Agenda Ready
File created: 1/6/2026 In control: Planning Commission
On agenda: 1/8/2026 Final action:
Title: Public hearing, consideration, and possible action regarding PUD-002550-2025 (Planned Unit Development) and BAZ-002374-2025 (Rezoning), D&B Processing, 9.15 acres, AG (Agricultural) to IL (Industrial Light)/PUD-002550-2025, abrogation of PUD-193, located one-half mile south of Washington Street (91st Street), one-half mile east of the Creek Turnpike
Attachments: 1. 2-Case Map, 2. 3-Aerial, 3. 4-Comprehensive Plan, 4. 5-PUD-002550-2025 Design Statement
Broken Arrow Planning Commission
01-08-2026

To: Chair and Commission Members
From: Community Development Department
Title:
title
Public hearing, consideration, and possible action regarding PUD-002550-2025 (Planned Unit Development) and BAZ-002374-2025 (Rezoning), D&B Processing, 9.15 acres, AG (Agricultural) to IL (Industrial Light)/PUD-002550-2025, abrogation of PUD-193, located one-half mile south of Washington Street (91st Street), one-half mile east of the Creek Turnpike
End
Background:
Applicant: Rob Coday, Rob Coday Architect LLC
Owner: Doug Burgess, D&B Processing
Developer: D&B Processing
Engineer: Daryl Worley, Worley Consulting
Location: One-half mile south of Washington Street (91st Street), one-half mile east of the Creek Turnpike
Size of Tract 9.15 acres
Present Zoning: AG (Agricultural)
Proposed Zoning: IL (Industrial Light)/PUD-002550-2025
Comp Plan: Level 6 (Regional Commercial/Employment)

Planned Unit Development (PUD)-002550-2025, D&B Proccessing, is a proposed development consisting of 9.15 acres generally located one-half mile south of Washington Street (91st Street), one-half mile east of the Creek Turnpike. BAZ-002374-2025 is a concurrent request to change the underlying zoning on the property from AG (Agricultural) to IL (Industrial Light). The property is currently one unplatted lot.

This development is a proposed storage yard to serve the existing D&B Processing facility across East Gary Street to the south. This property, along with the property to the east, was approved as part of PUD-193 and BAZ-1818 on November 8, 2008 for Coach Port storage facility. The property to the east developed per PUD-193, with the subject property currently under consideration initially planned as a second phase of development. The second phase never developed and was not platted along with the Coach Port subdivision. PUD-193 restricts the uses on this parcel to indoor RV storage, and the current developer would like to abrogate PUD-...