Title: Ratify the approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements Project (2454140)
Attachments: 1. Verdigirs_River_WTP_Raw_Water_Pump_-_PCO1_36_Inch_Mag_Meter_54
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 06-01-2026

 

Title:

title

Ratify the approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements Project (2454140)

End

 

Background:

The Verdigris River Water Treatment Plant Raw Water Pump Station Improvements will upgrade the electrical system and install another raw water pump.   

Change Order #1 addresses the following additions/deletions/changes to the contract:

-                     Replace a 36” flow meter at the raw water project. 

Total time added to contract is:

-                     28 weeks for procurement.

 

 The total cost for Change Order #1 amounts to $77,955.00

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0

This Change Order(s):                                                               $77,955.00

Total Cost of Change Orders:                                          $77,955.00

Original Contract Amount:                                          $1,094,400.00

Revised Contract Amount:                                          $1,172,355.00

 

Percent Change in Contract:                                          7.12%

Applicable to Comp. Bid Act:                     7.12%

Cost:                                                                ($77,955.00)

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, PE, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          PCO1 36 Inch Mag Meter
 

Recommendation:

recommend

Approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements Project (2454140)

end