Broken Arrow Municipal Authority
Meeting of: 06-01-2026
Title:
title
Ratify the approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements Project (2454140)
End
Background:
The Verdigris River Water Treatment Plant Raw Water Pump Station Improvements will upgrade the electrical system and install another raw water pump.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Replace a 36” flow meter at the raw water project.
Total time added to contract is:
- 28 weeks for procurement.
The total cost for Change Order #1 amounts to $77,955.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $77,955.00
Total Cost of Change Orders: $77,955.00
Original Contract Amount: $1,094,400.00
Revised Contract Amount: $1,172,355.00
Percent Change in Contract: 7.12%
Applicable to Comp. Bid Act: 7.12%
Cost: ($77,955.00)
Funding Source: OWRB Loan
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: PCO1 36 Inch Mag Meter
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Crossland Heavy Contractors for the Verdigris River WTP Raw Water Pump Station Improvements Project (2454140)