Broken Arrow City Council
Meeting of: 12-15-2015
To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Approval of and authorization to execute an Agreement for Professional Consultant Services (Architect-Engineer agreement) for final design and construction documents of the Turnberry Detention Pond Improvements
End
Background:
The City of Broken Arrow, with the 2011 G.O. Bond, dedicated funding towards design and construction of stormwater detention facility improvements to the Turnberry subdivision dry detention facility. The project includes upgrading the existing Dearborn Street cross street culvert immediately downstream from the detention pond. Utley & Associates, LLC was selected by the City to prepare the final design and construction documents for the detention facility and roadway culvert improvements. The authorized funding for the project is $200,000.00. The negotiated amount of the agreement is $28,500.00. The Architect-Engineer Agreement is attached.
Staff recommends approval of the Agreement for Professional Consultant Services with Utley & Associates, LLC. Funding for the design will be from the 2011 G.O. Bond sale.
Cost: $28,500.00
Prepared By: Douglas L. Tiffany, P.E., Director of Engineering and Construction
Reviewed By: Finance Department
Legal Department
Acting Assistant City Manager
Approved By: Michael L. Spurgeon, City Manager
Attachments: Architect-Engineer Agreement
Recommendation:
Approve the Agreement for Professional Consultant Services with Utley & Associates LLC, and authorize its execution.