LEGISLATIVE RESEARCH CENTER
File #: 16-1480    Name:
Type: Consent Item Status: Agenda Ready
File created: 12/13/2016 In control: Broken Arrow City Council
On agenda: 12/20/2016 Final action:
Title: Approval of and authorization to execute Change Order C05 for Construction Contract Number 161708, Farmers Market Interactive Water Feature
Attachments: 1. Change Order #5 Supporting Documents

Broken Arrow City Council

                                                                                               Meeting of: 12-20-16

                                                                                    

To:                     Mayor and City Council

From:                     Department of Engineering and Construction

Title: 

title

                     Approval of and authorization to execute Change Order C05 for Construction Contract Number 161708, Farmers Market Interactive Water Feature

End

Background:

The Rose District Farmers Market Water Feature is an approximately 1200-square-foot recirculating water feature located along the east boundary of the Farmers Market in the Rose District, 418 South Main Street.  The finished surface of the water feature will be granite pavers supported by a pedestal system over a concrete basin.  Site work consists of concrete and brick paving, masonry walls, lighting, and relocation of utilities. The construction contract was advertised for bids on February 23 and bids were opened on March 24, 2016.  Two (2) bids were received.  The awarded low bid was submitted by Magnum Construction, Inc., in the amount of $1,322,541.00, including the allowances for the three procurement contracts. 

 

This Change Order #5 addresses the following additions to the contract:

 

1.  Total Number of Days Added by this Change Order:                                                                                                         

      - Proposal Request #10-14; Work within this CO will not affect the contract time.

                                                                                                         

2.  Proposal Request #10: Provide and install electrical contractors to pump skid per COBA direction to enable emergency shutdown of show pumps only and keep remainder of system operational. Work performed previously under COBA direction during construction.                     

Cost $5,036.00                     

3.  Proposal Request #11: Provide and install electrical surge suppressor at Interactive Water Feature electrical service panel. Directive to resolve power surge problems reported by Parks Department during operation.

                                          Cost $4,137.00

4. Proposal Request #12: Replace existing skate deterrent installed during construction at the seat walls surrounding the Interactive Water Feature with the streetscapes project matching Maple Leaf skate deterrent.

                                          Cost $3,856.00

5. Proposal Request #13: Remove and replace existing IWF Rules sign panel with the revised panel verbiage noted by COBA.

                                          Cost $2,00.00

 

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $46,555.00

This Change Order:                                                               $15,029.00

Total Cost of Change Orders:                                          $61,584.00

Original Contract Amount:                                          $1,322,541.00

Revised Contract Amount:                                          $1,384,125.00

Percent Change in Contract:                                          4.66% (all applicable to 15% limitation)


Cost:                                                                $15,029.00

Prepared By:                                           Alex Mills, P.E, Director of Engineering and Construction

Reviewed By:                                          Finance Department
                                    Assistant City Manager - Operations
                                    Legal Department
                                 

Approved By:                      Michael L. Spurgeon, City Manager
                             

Attachments:                                          161708 Change Order #5 with associated Proposal Requests & RFI’s

Recommendation:

Approve Change Order #05 for the Farmers Market Interactive Water Feature project and authorize its execution.