Title: Approval of and authorization to execute a Channel and Regional Detention Facility agreement between Immanuel Evangelical Lutheran Church, Inc. and the City of Broken Arrow, located approximately quarter mile south of Kenosha and east side of Aspen Avenue, Broken Arrow, Tulsa County, State of Oklahoma
Attachments: 1. Contract Agreement, 2. Opinion of Probable Cost, 3. ILC Drainage Improvements Plans

Broken Arrow City Council

Meeting of: 12-20-2016

 

To:                     Mayor and City Council Members

From:                     Development Services Department

Title: 

title

                     Approval of and authorization to execute a Channel and Regional Detention Facility agreement between Immanuel Evangelical Lutheran Church, Inc. and the City of Broken Arrow, located approximately quarter mile south of Kenosha and east side of Aspen Avenue, Broken Arrow, Tulsa County, State of Oklahoma

End

Background:                     Immanuel Evangelical Church (IEL) approached the City in 2015 regarding drainage erosion along a branch of upper Haikey Creek.  The Creek has washed away a large area adjacent to the west abutment and scoured away the embankment on both sides of the channel east of Aspen that is undermining sewer service line, the Church drive and dental parking lot.  Most of the material that has eroded has deposited in the regional pond to the east of Aspen on the Church property.  The detention pond is a flow-by type facility that drains back to the Creek before flowing south into Country Aire Subdivision. 

 

                      The Creek drains most of the Kenosha and Aspen Intersection and surrounding areas.  The Creek daylights along and parallel to Aspen in front of the Church before entering a large double box skewed culvert.  The culvert directs the drainage due west along the Church property line with the Aspen Business Park before turning south toward Country Aire subdivision.  When the Creek turns south, there is a regional flow-by detention facility.

                     

                     When the area developed and the detention pond was constructed in the late 1990s to early 2000s, an overland drainage easement was prepared for the detention pond but never executed. 

 

                     In working with the Church and their Consultant, City staff agreed to participate in a channel and detention pond improvement project, along with a new overland drainage easement covering the regional detention pond.  The easement documents are included as a separate submittal under the Consent agenda for acceptance and filing.

 

                     The City received internal approval to utilize Fee in-lieu-of funds up to $100,000 for the channel and detention pond project.  A contract agreement was prepared along with design plans.  The channel will be reshaped and include various erosion and stability measures, encasement of the sewer service line crossing and regrading of the detention pond back to original design. 

 

                     The Engineers cost estimate is $247,404.68.  The City’s portion is $100,000 and the Church would fund the remainder, $147,404.68.  We are anticipating the project will bid in January and construction to commence in March.

 

                                                               City staff has reviewed the contract agreement and recommends approval.

 

Cost:                                                                $100,000 (Stormwater Fee in-lieu-of Fund)

 

Prepared By:                                           Michael W. Skates, P.E., CFM, Development Services Director

 

Reviewed By:                                          Engineering Department
                                    Streets and Stormwater
                                    Finance Department
                                    Assistant City Manager - Operations
                                    Legal Department

Approved By:                      Michael L. Spurgeon, City Manager

 

Attachments:                                          Contract Agreement

                                    Opinion of Probable Cost

                                    Draft Final Plan Set

 

Recommendation:                     Approve the channel and regional detention facility agreement and authorize its execution.