Broken Arrow City Council
Meeting of: 05-20-2025
Title:
title
Consideration, discussion, and possible approval of and authorization to execute a Professional Consultant Agreement with CEC Corporation for the Tucson Street Improvements from Olive Avenue to Aspen Avenue Including Intersection Improvements at Olive Avenue (Project No. ST25300)
End
Background:
Due to existing infrastructure conditions as well as proposed growth and development, staff have solicited for qualifications for engineering design services for the Tucson Street Improvements from Olive Avenue to Aspen Avenue Including Intersection Improvements at Olive Avenue project. After reviewing and evaluating the submitted statement of qualifications from multiple firms, Engineering & Construction Department staff selected CEC Corporation to negotiate a professional consultant agreement.
The professional consultant agreement the staff negotiated with CEC Corporation for this project includes the design of either widening the existing two-lane asphalt roadway to a three-lane section with the addition of shoulders, open and/or closed drainage/storm sewer system, sidewalk/trail, as well as design of water and sewer line relocations/upgrades as required; or, widening the existing the existing two-lane asphalt roadway to a five-lane section with curb and gutter, open and/or closed drainage/storm sewer system, sidewalk/trail, as well as the design of water and sewer line relocations as required. Intersection improvements at Olive Avenue will include either a roundabout or signalized intersection. Bridge and another drainage structure improvements are also part of this project. The project shall also include services for the following: identification of right-of-way needs, preparation of right-of-way acquisition documents, assistance during acquisition, identification of the need for utility relocations, and the coordination of utility relocations.
Cost: $549,210.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, P.E., Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: Tucson Steet Improvements Agreement-ST25300
Recommendation:
recommend
Approve and authorize execution a Professional Consultant Agreement with CEC Corporation for the Tucson Street Improvements from Olive Avenue to Aspen Avenue Including Intersection Improvements at Olive Avenue project (Project No.: ST25300)
end