LEGISLATIVE RESEARCH CENTER
File #: 16-524    Name:
Type: Consent Item Status: Passed
File created: 5/9/2016 In control: Broken Arrow City Council
On agenda: 5/17/2016 Final action: 5/17/2016
Title: Approval of bids received, award of the lowest responsible bid to Ark Wrecking Company of Oklahoma, Inc., and approval of and authorization to execute a construction contract for demolition of the former Assembly of God Church owned by the City of Broken Arrow and located at 305 North Main Street (Project No. 161714)
Attachments: 1. 160509 Certified Bid Tab Demolition of Surplus Property 305 N Main

Broken Arrow City Council

                                                                                               Meeting of: 05-17-16

                                                                                    

To:                     Mayor and City Council

From:                     Department of Engineering and Construction

Title: 

title

                     Approval of bids received, award of the lowest responsible bid to Ark Wrecking Company of Oklahoma, Inc., and approval of and authorization to execute a construction contract for demolition of the former Assembly of God Church owned by the City of Broken Arrow and located at 305 North Main Street (Project No. 161714)

End

Background:

At a special meeting on February 10, 2016, the Broken Arrow City Council approved the purchase of the property at 305 North Main Street, the former Assembly of God Church, including an abandoned two-story building that had been used for a church and other purposes.  An asbestos survey of the building was completed March 16, 2016, and the conclusion was that there were no asbestos-containing materials in the structure.  Engineering and Construction Department Staff advertised for demolition of the building on April 13 and 20, 2016, and held a mandatory pre-bid meeting on April 28, 2016.  Bids were opened on May 5, 2016.  Six (6) bids were received, but one was rejected because the bidder did not return the entire bid book as instructed. 

 

The low bid of $87,140.00 was submitted by Ark Wrecking Company of Oklahoma, Inc.  The engineer’s estimate was $365,172.00.  The Certified Bid Tabulation is attached.  Staff recommends award of the contract to Ark Wrecking Company of Oklahoma, Inc., in the amount of $87,140.00. 

Funding for this project is from Sales Tax Capital Improvements.


Cost:                                                                $87,140.00                               

Prepared By:                                           Jeff Bigby, P.E., Director of Engineering and Construction

 

Reviewed By:                                          General Services Department
                                    Finance Department
                                   Assistant City Manager - Operations
                                   Legal Department                        

 

Approved By:                      Michael L. Spurgeon, City Manager                                    

Attachments:                                          Certified Bid Tabulation

Recommendation:                     Award of the lowest responsible bid to Ark Wrecking Company of Oklahoma, Inc., and approve and authorize execution of a construction contract for demolition at 305 North Main Street.