Title: Consideration, discussion, and possible approval of SITE-003113-2026, the building elevations for CSI Aerospace, 10 acres, IL (Industrial Light), located one-eighth mile east of Olive Avenue (129th East Avenue), south of West Florence Street (111th Street)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Planning Commission

10-08-2026

 

To:                     Chair and Commission Members

From:                     Community Development Department

Title: 

title

                     Consideration, discussion, and possible approval of SITE-003113-2026, the building elevations for CSI Aerospace, 10 acres, IL (Industrial Light), located one-eighth mile east of Olive Avenue (129th East Avenue), south of West Florence Street (111th Street)

End

Background:

Applicant:                                          GH2 Architects

Owner:                     Broken Arrow Economic Development Authority

Developer:                                          N/A

Engineer:                                          Wallace Design Collective

Location:                                          One-eighth mile east of Olive Avenue (129th East Avenue), south of West
  Florence Street (111th Street)

Size of Tract                                          10 acres

Number of Lots:                     1

Present Zoning:                     IL (Industrial Light)

Comp Plan:                                          Level 7 (Major Industrial)

 

A site plan was submitted for a proposed 38,000-square-foot industrial facility located one-eighth mile east of Olive Avenue (129th East Avenue), south of W. Florence Street (111th Street). The property is zoned IL (Industrial Light).

 

The applicant is proposing to reduce the primary building materials requirement for this facility. Under Section 3-3-5: Industrial Light (IL), G. Additional Design Standards, it states primary materials include: masonry, such as brick or stone, stucco, glass, such as glass curtain walls or glass block, concrete panels, or cementitious siding. Secondary building materials include metals including metal panels and architectural metal, Exterior Insulated Finished Systems (EIFS), siding such as wood shingle or wood clapboard, or masonry materials other than brick and stone may only make up 25 percent of exterior walls visible from the public realm. Proposals that include those materials on more than 25 percent of one or more exterior walls visible from the public realm shall be reviewed by the Planning Commission.

 

Planning Commission reviewed this site plan at their regular meeting on September 24, 2026. A motion was made to table this item until the next regular meeting of October 8, 2026, when information on leadership’s vision for the Innovation District development could be obtained. The applicant has since withdrawn this application.

 

 

Attachments:                           None                                                                                                                                                
                                                              

Recommendation:                      

Staff recommends that the reduction in primary building materials requirement be denied per the building material requirements under Section 3-3-5: Industrial light (IL), G. Additional Design Standards.

 

Reviewed By:                                 Jane Wyrick

 

Approved By:                     Rocky Henkel

 

RLB