Title: Acceptance of a Utility Easement for Parcel 10.0 and a Temporary Construction Easement for Parcel 10.1, consisting of 0.004 Acres of permanent utility easement and 0.002 Acres of temporary construction easement, respectively, on property located at 490 East New Orleans Street in Broken Arrow, Oklahoma, in the Southeast Quarter of Section 23, Township 18 North, Range 14 East, Tulsa County, Oklahoma, from Michael Bailey and Jessica Bailey, and authorization of payment in the amount of $500.00 for the New Orleans & 9th Street Sanitary Sewer Line, Parcels 10.0 and 10.1 (Project No. S.26040)
Attachments: 1. Acceptance letter, 2. Affidavit, 3. Conditions and Request for Payment, 4. Utility Easement, 5. Temporary Construction Easement
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 08-03-2026

 

Title:

title

Acceptance of a Utility Easement for Parcel 10.0 and a Temporary Construction Easement for Parcel 10.1, consisting of 0.004 Acres of permanent utility easement and 0.002 Acres of temporary construction easement, respectively, on property located at 490 East New Orleans Street in Broken Arrow, Oklahoma, in the Southeast Quarter of Section 23, Township 18 North, Range 14 East, Tulsa County, Oklahoma, from Michael Bailey and Jessica Bailey, and authorization of payment in the amount of $500.00 for the New Orleans & 9th Street Sanitary Sewer Line, Parcels 10.0 and 10.1 (Project No. S.26040)

End

 

Background:

The properties in the attached Utility Easement and Temporary Construction Easement are being conveyed to the City of Broken Arrow, a municipal corporation, from Michael Bailey and Jessica Bailey, the owners. Parcel 10.0 consists of 0.004 Acres of permanent utility easement, and Parcel 10.1 consists of 0.002 Acres of temporary construction easement, located at 490 East New Orleans Street in Broken Arrow, Oklahoma in the Southeast Quarter of Section 23, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma.  Michael Bailey and Jessica Bailey have accepted the following offer, made subject to City Council approval:

Parcel 10.0

Permanent Utility Easement: 0.004 Acres @ $65,000/Acre x 75%= $195

Parcel 10.1

Temporary Construction Easement: 0.002 Acres/106.74 (SF) @ $65,000/Acre x 10% = $13 Settlement Cost: $290.00

Total Just Compensation Amount (Rounded) = $500.00

A copy of the signed acceptance of the City’s offer is attached, as is the Utility Easement. Payment of the compensation amount is on the August 3, 2026 City Council Claims List.

 

Cost:                                                                $500.00

Funding Source:                     Fund 350/351

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Acceptance letter
                                    Affidavit
                                    Conditions and Request for Payment
                                    Utility Easement
                                    Temporary Construction Easement
                          

 

 

 

Recommendation:

recommend

Accept the Utility Easement and Temporary Construction Easement and                authorize payment.