Title: Approval of and authorization to execute Agreement, Gas Facilities Relocation, between Oklahoma Natural Gas and the City of Broken Arrow, along South Aspen Ave between West Tucson Street and West Jasper Street (Project Number ST2031)(ONG Phase 3 Relocations)
Attachments: 1. 20250725-ONG Phase 3 Relocation Agreement.LegalSigned-ST2031
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 8-4-2025

 

Title:

title

Approval of and authorization to execute Agreement, Gas Facilities Relocation, between Oklahoma Natural Gas and the City of Broken Arrow, along South Aspen Ave between West Tucson Street and West Jasper Street (Project Number ST2031)(ONG Phase 3 Relocations)

End

 

Background:

The City of Broken Arrow plans to improve South Aspen Ave between West Tucson Street and West Jasper Street as part of the 2018 GO Bond. In order to accommodate the new construction, existing Oklahoma Natural Gas Company (ONG) medium pressure gas facilities need to be relocated. Portions of these existing facilities are located within existing private ONG easements, and as such, the City must reimburse ONG for the cost of relocating those portions of the facilities. ONG will bear the cost of relocating the portions of the facilities that do not occupy private easements, or for improvements (betterments) to their facilities completed as part of this project.

The total anticipated construction cost for this work is $686,200.00. Of which, the City portion is $562,404.00 (82.10%). ONG’s share is $122,797.00 (17.90%), which includes any betterment. The attached Agreement details these costs and serves as authorization for ONG to begin the relocation process.

Staff recommends approval of the Agreement with ONG to relocate the medium pressure gas facilities for an estimated cost to the City of $562,404.00.

 

Cost:                                                                $562,404.00

Funding Source:                     2018 General Obligation Bond

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Agreement, Gas Facilities Relocation, between ONG and City of Broken Arrow

Recommendation:

recommend

Approve and authorize execution of Agreement, Medium Pressure Gas Facilities Relocation, between Oklahoma Natural Gas and the City of Broken Arrow, along South Aspen Ave between West Tucson Street and West Jasper Street (Project Number ST2031)(ONG Phase 3 Relocations)

end