File #: 26-337    Name:
Type: Consent Item Status: Agenda Ready
File created: 2/24/2026 In control: Broken Arrow City Council
On agenda: 3/3/2026 Final action:
Title: Acceptance of a Utility Easement consisting of 10,251.29 square feet of utility easement from Darrell Schulze and Mal Ye Schulze, Trustees of the Schulze Family Revocable Trust, Dated April 18, 2016, on property located at 11245 South Elm Place in Broken Arrow, Oklahoma, located in the Northwest Quarter of Section 35, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma for the 16-inch Waterline Loop Elm & Florence, Parcel 5.0 (Project No. WL23090)
Attachments: 1. Acceptance Letter, 2. Affidavit, 3. Conditions and Request for Payment, 4. Utility Easement
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 03-03-2026

 

Title:

title

Acceptance of a Utility Easement consisting of 10,251.29 square feet of utility easement from Darrell Schulze and Mal Ye Schulze, Trustees of the Schulze Family Revocable Trust, Dated April 18, 2016, on property located at 11245 South Elm Place in Broken Arrow, Oklahoma, located in the Northwest Quarter of Section 35, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma for the 16-inch Waterline Loop Elm & Florence, Parcel 5.0 (Project No. WL23090)

End

 

Background:

The attached Utility Easement is being conveyed to the City of Broken Arrow from Darrell Schulze and Mal Ye Schulze, Trustees of the Schulze Family Revocable Trust, Dated April 18, 2016, the owner. Parcel 5.0 consists of 10,251.29 square feet of utility easement and is for the 16-inch Waterline Loop Elm & Florence, located in the Northwest Quarter of Section 35, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma.  Darrell Schulze and Mal Ye Schulze, Trustees of the Schulze Family Revocable Trust, Dated April 18, 2016, have accepted the following offer, made subject to City Council approval:

 

Permanent Utility Easement: 10,251.29 SQUARE FEET (SF) @ $2.60 SF X 75% = $19,990

Improvements Acquired:

Mature Trees 19 x $400 each = $7,600

Small Trees: 9 x $200 each = $1,800                                                                                    Total Improvements: $9,400

Total Just Compensation Amount (Rounded) = $29,390

 

A copy of the signed acceptance letter is attached, as is the Utility Easement.  Payment of the compensation amount is on the March 3, 2026, City Council ClaimsList.

 

Cost:                                                                $29,390.00

Funding Source:                     OWRB Loan

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Utility Easement                                   
                                    Acceptance Letter
                                    Conditions for Payment
                                    Affidavit  

Recommendation:

recommend

Accept the Utility Easement

 