Broken Arrow City Council
Meeting of: 06-20-16
To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Approval of and authorization to execute Change Order C01 for Construction Contract ST1508 with Pavement Conservation Specialists, Inc.; Village Square I, II, III Street Improvements
End
Background:
The 2011 Streets General Obligation Bond included a project described as “Village Square: Repair, mill and overlay streets with curb repairs and construct handicap access ramps as required.” Bonds for the project were sold in December 2014. Engineering and Construction Staff prepared bidding documents, and the project was advertised for bids on October 5 and 12, 2015. Bids were opened on October 27, 2015, and three (3) bids were received. The low bidder was Pavement Conservation Specialists, Inc., with a proposal of $796,582.00. Construction Notice to Proceed was issued January 11, 2016, and Substantial Completion was issued May 31, 2016.
This Change Order #1 addresses the following additions to the contract:
1. Total Number of Days Added by this Change Order:
- Due to weather delays in the project, an extension of 21 days is requested
2. Reconciling Changes: Due to site conditions varying from design parameters, field adjustments of the plan quantities by the City contract administrator was authorized. These changes in quantities are summarized on the attached "Project Final Quantities Report". The listed change order cost is to adjust the original contract value to the reflected installed contract value.
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order: $-716.53
Total Cost of Change Orders: $-716.53
Original Contract Amount: $796,582.50
Revised Contract Amount: $795,865.97
Percent Change in Contract: -0.09%
Cost: $-716.53
Prepared By: Jeff Bigby, P.E, Acting Director of Engineering and Construction
Reviewed By: Engineering and Construction Department
Finance Department
Assistant City Manager - Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: ST1508 Change Order C01 with associated Contract Documents
Recommendation:
Approve Change Order C01 for the Village Square Street Improvements Project and authorize its execution.