Title: Approval of and authorization to execute Resolution No. 1724, a Resolution authorizing acceptance of a General Warranty Deed for Parcel 11.0, consisting of 3,826 square feet of permanent Right-of-Way located at 4677 South 209th East Avenue in Broken Arrow, Oklahoma, in the Southwest Quarter of Section 29, Township 19 North, Range 15 East, Wagoner County, Oklahoma, from Christian Cubero, for the 37th Street Roadway Widening from Omaha Street to Dearborn Street, Parcel 11.0 (Project No. ST21390)
Attachments: 1. Acceptance letter, 2. Affidavit, 3. Conditions and Request for Payment, 4. General Warranty Deed, 5. RESOLUTION NO 1724
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 12-02-2025

 

Title:

title

Approval of and authorization to execute Resolution No. 1724, a Resolution authorizing acceptance of a General Warranty Deed for Parcel 11.0, consisting of 3,826 square feet of permanent Right-of-Way located at 4677 South 209th East Avenue in Broken Arrow, Oklahoma, in the Southwest Quarter of Section 29, Township 19 North, Range 15 East, Wagoner County, Oklahoma, from Christian Cubero, for the 37th Street Roadway Widening from Omaha Street to Dearborn Street, Parcel 11.0 (Project No. ST21390)

End

Background:

The attached General Warranty Deed is being conveyed to the City of Broken Arrow, a municipal corporation, from Christian Cubero the owner. Parcel 11.0 consists of 3,826 square feet of permanent Right-of-Way, in the Southwest Quarter of Section 29, Township 19 North, Range 15 East, Wagoner County, State of Oklahoma.  Christian Cubero has accepted the following offer, made subject to City Council approval:

Permanent Right of Way: 0.09 Acres @ $71,000/Acre = $6,390

Improvements Acquired: Large Trees 2 each @ $1,000 each = $2,000; Crepe Myrtle Bushes 4 each @ $400.00 each = $1,600; 8’ x 25’ gravel drive 200 SF x $2.00/SF = $400; 9’ x 25’ gravel drive 225 SF x $2.00/SF = $450                            Total Improvements Acquired $4,450

Proximity damages: $10,164                                          

Cost to cure Damages: Install tree/bush or fence line: 1 x $3,000 each = $3,000

Settlement Cost: $2,973

 

Total Just Compensation Amount (Rounded) = $26,980

A copy of the signed acceptance of the City’s offer is attached, as is the General Warranty Deed.

Payment of the compensation is on the December 2, 2025 City Council Claims List.

 

Cost:                                                                $26,980.00

Funding Source:                     2018 GO Bond

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Resolution No. 1724
                                    Acceptance Letter
                                    General Warranty Deed
                                    Conditions and Request for Payment
                                    Affidavit

 

Recommendation:

recommend

Approve and authorize execution of Resolution No. 1724

 