Title: Approval and authorization to execute Change Order #1 with R&L Construction, LLC on Construction Contract #ST1616B; Washington Street Improvements from Garnett Rd. to Olive Ave; Reinforced Concrete Package
Attachments: 1. ST1616B - Change Order #1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of:  3-2-2021

 

Title:

title

Approval and authorization to execute Change Order #1 with R&L Construction, LLC on Construction Contract #ST1616B; Washington Street Improvements from Garnett Rd. to Olive Ave; Reinforced Concrete Package

End

 

Background:

The Washington Street (91st Street South) Improvements from Garnett Road to Olive Avenue (129th East Avenue) is a 2014 Streets General Obligation Bond project. Original project number is ST1616. The Bond issue calls for widening Washington from Garnett Road to Olive Avenue (129th Est Avenue) including all appurtenances.  The improvements on Washington Street from Garnett Road to Olive Avenue include approximately 1.0 mile of roadway widening from 3 to 5 lanes with asphalt pavement along with the addition of concrete curb and gutter, sidewalk, trail, driveways, water line relocation, traffic signalization, enclosed storm sewer system, retaining wall, RCB bridge widening and RCP cross drain extension.

This construction contract consists of the reinforced concrete items from the ST1616 contract. This work includes the following items: reinforced concrete box culvert extension with wing walls, CET end treatments for a three span 72-inch reinforced concrete pipe, five end sections for a 10’ x 3’ reinforced concrete box, 440 linear foot retaining wall with a stem wall on each end, 213 linear foot parapet wall with moment slab, associated ornamental fences, and an add alternates for 5,125 linear foot multi-use trail and adjacent 1 ½ inch high density polyethylene pipe.

The project was advertised for bid on September 8th and 15th, 2020. Bids were opened on September 29, 2020, with the apparent low bidder was R&L Construction, LLC at the time of bid opening with a base bid of $1,139,481.65, Add Alternate 1 bid of $243,024.00, Add Alternate 2 bid of $208,426.25 for a total bid of $1,590,931.90. A Notice to Proceed was issued shortly after award via council.

This Change Order #1 addresses the following additions to the contract:

 

-                     As directed by the City of Broken Arrow forces, the contractor is to fine grade the sloped embankments surrounding the south side outfall at the 72” RCP at STA 214+80. Upon completion of the fine grading the contractor shall install varying sizes of rock rip rap within the outfall constituting approximately 2350 Square Feet of floodway. The Rip Rap will also be grouted with CLSM to provide structure and prevent erosion.

 

-                     As directed by the City of Broken Arrow forces, the contractor shall remove, disposal, and reinstall “like kind” 6 foot perimeter fencing along the alignment between 224+00 & 228+50. This replacement of cedar perimeter fencing is due to conflicts with the installation of the new 10’ wide trail and drainage flume. The field measured length of perimeter fencing is 594 linear feet.

 

Contract Time Adjustments:

                     None required due to this change.

 

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0.00

This Change Order:                                                               $49,427.00

Total Cost of Change Orders:                                          $49,427.00

Original Contract Amount:                                          $1,590,931.90

Revised Contract Amount:                                          $1,640,358.90

Percent Change in Contract:                                          3.11%

Applicable to Comp. Bid Act:                     3.11%

 

 

 

Cost:                                                                $49,427.00

Funding Source:                     2014 General Obligation Bonds

Requested By:                      Ethan J.L. Edwards; Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          ST1616B - Change Order #1

 

Recommendation:

recommend

Approve and authorize the execution of Change Order #1 with R&L Construction, LLC on Construction Contract #ST1616B; Washington Street Improvements from Garnett Rd. to Olive Ave; Reinforced Concrete Package