LEGISLATIVE RESEARCH CENTER
File #: 24-191    Name:
Type: General Business Status: Agenda Ready
File created: 1/29/2024 In control: Broken Arrow City Council
On agenda: 2/6/2024 Final action:
Title: Consideration, discussion, and possible approval of and authorization to execute Change Order No. 1 with Cobalt Coatings for construction contract 2453160 - TS23120; Signalization Pole Improvements project
Attachments: 1. 2453160-TS23120 Change Order #1 - Additional Pole Painting

Broken Arrow City Council

Meeting of: 02-06-2024

 

Title:

title

Consideration, discussion, and possible approval of and authorization to execute Change Order No. 1 with Cobalt Coatings for construction contract 2453160 - TS23120; Signalization Pole Improvements project

End

 

Background:

The Engineering and Construction Department had designed and bit out the Signalization Pole Improvement Project, which includes coating existing signal poles in a black coating and at select locations install electrical receptacle boxes & decorative banner arms. 

The Base Bid includes all items related to the Kenosha Street intersections of Aspen Avenue, Elm Place, Main Street, 9th Street, and 23rd Street, and the intersections of Main Street at Houston Street and Main Street at Washington Street. Alternate 1 Bid includes all items related to the intersection of Elm Place at Washington Street. Alternate 2 Bid includes all items related to the intersection of Aspen Avenue and New Orleans Street. Alternate 3 Bid includes all items related to the intersection of Aspen Avenue and Florence Street.

The project was advertised according to the Competitive Bid Act and bids were opened on October 3, 2023, with the lowest responsible combined bid being Cobalt Coatings for $169,525.00.

This Change Order #1 addresses the following additions /or deletions to the contract:                                                                                                                                                                                                                  

At the request of the City, the contractor and City staff have negotiated the continuation of the signalization pole painting applications to an addition (27) locations throughout Broken Arrow. These locations are identified as written below within this change order. The mobilization and traffic control for these additional locations, is negotiated to the lump sum value noted in CO1-1; the base bid Line Item # 103 (PL) Traffic Items (Paint Mast Arm Poles) shall be overrun to account for each of the new identified locations accordingly.

Locations of Work:

                     Aspen & Albany                                                                                    

                     Aspen and Detroit                                                                                    

                     Aspen and Houston                                                                                    

                     Albany and Stoneridge                                                                                    

                     Elm and Concord                                                                                    

                     Elm and Albany                                                                                    

                     Elm and Stonewood                                                                                    

                     Elm and Queens Circle                                                                                    

                     Elm and Broadway                                                                                    

                     Elm and Florence                                                                                    

                     Elm and Quanah Place                                                                                    

                     Elm and Tucson                                                                                     

                     Main and Pittsburgh Place                                                                                    

                     Main and Richmond                                                                                    

                     New Orleans and South 1st Place                                                                                    

                     Lynn Lane and Juneau                                                                                    

                     Lynn Land and Albany                                                                                    

                     Lynn Lane and Hillside                                                                                    

                     Lynn Lane and Lansing                                                                                    

                     Lynn Lane and Flight Safety                                                                                    

                     Lynn Lane and Dallas                                                                                    

                     Lynn Lane and Houston                                                                                    

                     County Line and Hillside                                                                                    

                     Kenosha and 209th                                                                                     

                     New Orleans St. & County Line                                                                                    

                     Washington St & Olive St.                                                                                                                                                                        

 

Funding for this work is being covered by the original budget allocated within the Fund 342 - Street Light Fund

Additional Time in Contract:

Due to the increased volume of locations, the contractor plans on (2) separate mobilizations for this work with the first planned in March 2024 and the second to be worked out with City staff. The completion of this project shall be completed by October 2024.

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $0.00

This Change Order:                                                               $313,600.00

Total Cost of Change Orders:                                          $313,600.00

Original Contract Amount:                                          $169,525.00

Revised Contract Amount:                                          $483,125.00

Percent Change in Contract:                                          284.99%

Applicable to Comp. Bid Act:                     14.75% (15% Max Allowable)

 

Cost:                                                                $313,600.00

Funding Source:                     Fund 342 - Street Light Fund

Requested By:                      Kenneth D. Schwab, PE, Acting Director of Engineering & Construction

Approved By:                      City Manager’s Office

Attachments:                                          2453160-TS23120 Change Order #1 - Additional Pole Painting

 

Recommendation:

recommend

 Approve and authorize execution of Change Order No. 1 with Cobalt Coatings for construction contract 2453160 - TS23120; Signalization Pole Improvements project

end