Consideration, discussion, and possible approval of and authorization to execute Change Order No. 1 with Cobalt Coatings for construction contract 2453160 - TS23120; Signalization Pole Improvements project
End
Background:
The Engineering and Construction Department had designed and bit out the Signalization Pole Improvement Project, which includes coating existing signal poles in a black coating and at select locations install electrical receptacle boxes & decorative banner arms.
The Base Bid includes all items related to the Kenosha Street intersections of Aspen Avenue, Elm Place, Main Street, 9th Street, and 23rd Street, and the intersections of Main Street at Houston Street and Main Street at Washington Street. Alternate 1 Bid includes all items related to the intersection of Elm Place at Washington Street. Alternate 2 Bid includes all items related to the intersection of Aspen Avenue and New Orleans Street. Alternate 3 Bid includes all items related to the intersection of Aspen Avenue and Florence Street.
The project was advertised according to the Competitive Bid Act and bids were opened on October 3, 2023, with the lowest responsible combined bid being Cobalt Coatings for $169,525.00.
This Change Order #1 addresses the following additions /or deletions to the contract:
At the request of the City, the contractor and City staff have negotiated the continuation of the signalization pole painting applications to an addition (27) locations throughout Broken Arrow. These locations are identified as written below within this change order. The mobilization and traffic control for these additional locations, is negotiated to the lump sum value noted in CO1-1; the base bid Line Item # 103 (PL) Traffic Items (Paint Mast Arm Poles) shall be overrun to account for each of the new identified locations accordingly.
Locations of Work:
• Aspen & Albany
• Aspen and Detroit
• Aspen and Houston
• Albany and Stoneridge
• Elm and Concord
• Elm and Albany
• Elm and Stonewood
• Elm and Queens Circle
• Elm and Broadway
• Elm and Florence
• Elm and Quanah Place
• Elm and Tucson
• Main and Pittsburgh Place
• Main and Richmond
• New Orleans and South 1st Place
• Lynn Lane and Juneau
• Lynn Land and Albany
• Lynn Lane and Hillside
• Lynn Lane and Lansing
• Lynn Lane and Flight Safety
• Lynn Lane and Dallas
• Lynn Lane and Houston
• County Line and Hillside
• Kenosha and 209th
• New Orleans St. & County Line
• Washington St & Olive St.
Funding for this work is being covered by the original budget allocated within the Fund 342 - Street Light Fund
Additional Time in Contract:
Due to the increased volume of locations, the contractor plans on (2) separate mobilizations for this work with the first planned in March 2024 and the second to be worked out with City staff. The completion of this project shall be completed by October 2024.
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order: $313,600.00
Total Cost of Change Orders: $313,600.00
Original Contract Amount: $169,525.00
Revised Contract Amount: $483,125.00
Percent Change in Contract: 284.99%
Applicable to Comp. Bid Act: 14.75% (15% Max Allowable)
Cost: $313,600.00
Funding Source: Fund 342 - Street Light Fund
Requested By: Kenneth D. Schwab, PE, Acting Director of Engineering & Construction
Approved By: City Manager’s Office
Attachments: 2453160-TS23120 Change Order #1 - Additional Pole Painting
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Cobalt Coatings for construction contract 2453160 - TS23120; Signalization Pole Improvements project