On agenda: 6/26/2025 Final action:
Title: Approval of LOT-002233-2025, Timber Ridge Business Park, 1 lot to 3 lots, 3.08 acres, IL (Industrial Light)/PUD-259, located one-half mile west of Evans Road (225th East Avenue) and south of Kenosha Street (71st Street)
Attachments: 1. 2-Case Map, 2. 3-Aerial, 3. 4-Exhibits
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Planning Commission

06-26-2025

 

To:                     Chairman and Commission Members

From:                     Community Development Department

Title: 

title

Approval of LOT-002233-2025, Timber Ridge Business Park, 1 lot to 3 lots, 3.08 acres, IL (Industrial Light)/PUD-259, located one-half mile west of Evans Road (225th East Avenue) and south of Kenosha Street (71st Street)

End

Background:

Applicant:                                          Glenn Murray, Tulsa Engineering & Planning

Owner:                     Cheryl Pfeffer

Developer:                                          N/A

Surveyor:                                          Tulsa Engineering & Planning

Location:                     Approximately one-half mile west of Evans Road (225th East Avenue) and south of Kenosha Street (71st Street).

Size of Tract                     3.08 acres

Number of Lots:                     1 existing, 3 proposed

Zoning:                                          IL (Industrial Light)/PUD-259

Comp Plan:                                          Level 6 (Regional Employment/Commercial)

 

Lot Split request LOT-002233-2025 involves 3.08 acres platted as Lot 1, Block 1, Timber Ridge Business Park, is zoned IL (Industrial Light)/PUD-259 and is located approximately one-half mile west of Evans Road (225th East Avenue) and south of Kenosha Street (71st Street).

 

PUD-259 was approved by the City Council on April 4, 2017. The PUD provided minimum lot area and frontage requirements as shown below. All lots created by this lot split meet the dimensional requirements of the PUD.

 

 

PUD-259

Tract A

Tract B

Tract C

Tract D

Minimum Area:

N/A

1.03 acres

1 acre

0.52 acres

0.52 acres

Minimum Frontage:

100’

400’+

137.46’

125’

125’

 

According to FEMA Maps, none of this property is located within the 100-year floodplain. Water and Sanitary Sewer are available to each lot.

 

Lot-002233-2025 was discussed by the Technical Advisory Committee on June 17, 2025. Oklahoma Natural Gas (ONG), Public Service Company of Oklahoma (PSO), Windstream, and Cox Communications did not indicate any issues with the proposed lot split.

 

Attachments:                                 Case map
                                    Aerial
                                    Exhibits and Legal Descriptions

                                                               

Recommendation:                     

Staff recommends LOT-002233-2025 be approved, subject to new warranty deeds for all parcels being brought simultaneously to the Planning & Development Division to be stamped prior to being recorded in Wagoner County.

                     

Reviewed by:      Amanda Yamaguchi

 

Approved by:     Rocky Henkel

 

 

ALY