LEGISLATIVE RESEARCH CENTER
File #: 15-093    Name:
Type: General Business Status: Passed
File created: 6/18/2015 In control: Broken Arrow City Council
On agenda: 7/7/2015 Final action: 7/7/2015
Title: Acknowledgement of bids received, as well as Stoney Creek Hospitality Corporation's award of the lowest and best bid to Tri-Star Construction, and approval of a contract for site earth work and construction of certain utilities and infrastructure for the Stoney Creek Conference Center and Hotel using Vision 2025 proceeds allocated to the City of Broken Arrow
Attachments: 1. Certified Bid Tabulation.pdf, 2. Site Plan.pdf

Broken Arrow City Council

Meeting of: 07-07-2015

 

To:                     Mayor and City Council

From:                     Development Services Department

Title:

title

                     Acknowledgement of bids received, as well as Stoney Creek Hospitality Corporation’s award of the lowest and best bid to Tri-Star Construction, and approval of a contract for site earth work and construction of certain utilities and infrastructure for the Stoney Creek Conference Center and Hotel using Vision 2025 proceeds allocated to the City of Broken Arrow

End

Background:

Stoney Creek Hospitality Corporation contracted with the Broken Arrow Economic Development Authority (BAEDA) and the City of Broken Arrow for the development of a Conference Center and Hotel.  Vision 2025 monies in the amount of $5,550,000.00 are dedicated to fund site infrastructure and pay for certain professional services.

 

Stoney Creek Engineering Company prepared plans associated with the site earth change work, a segment of water line, and an access drive.  Cowan Group Consulting, on behalf of Stone Creek, prepared bidding documents for the project.  The project was advertised for bids on May 8 and 15, 2015.  Bids were opened on June 4, 2015.  Seven (7) bids were received.  The Certified Bid Tabulation is attached.  The low bidder was Tri-Star Construction with a base bid proposal of $1,731,650.00 and an additive alternate 1 of $83,383.50 and an additive alternate 2 of $6,900.00.  The engineer’s estimate base bid was $2,742,114.60 and an additive alternate 1 of $91,656.90 and an additive alternate 2 of $11,340.00

 

Cowan Group Consulting recommended the base bid and additive alternate 1.  Additive alternate 2 was included in the event if additive alternate 1 came in too high on the mutual access drive on the eastern side of the property.

 

Cowan Group Consulting and City staff recommended Stoney Creek’s award of the contract to Tri-Star Construction for the base bid and additive alternate 1.  Funding for the improvements will be from the Vision 2025 excess funds.

 

Cost:                                                                $1,815,033.50 (Base Bid plus Additive Alternate 1)

Prepared By:                                           Michael Skates, P.E., CFM, Development Services Director

Reviewed By:                                          Department of Engineering and Construction
                                    Legal Department
                                    Assistant City Manager

Approved By:                      Russell M. Gale, Acting City Manager

Attachments:                                          Certified Bid Tabulation
                                    Site Plan

Recommendation:                     Acknowledge Stoney Creek Hospitality Corporation’s award of the lowest and best bid to Tri-Star Construction and its approval of a construction contract for site earth work and construction of certain utilities and infrastructure.