LEGISLATIVE RESEARCH CENTER
File #: 16-487    Name:
Type: Consent Item Status: Agenda Ready
File created: 4/27/2016 In control: Broken Arrow City Council
On agenda: 5/3/2016 Final action:
Title: Approval of Minor Change Order C02 for Construction Contract 166022, Central Park Electrical Upgrade
Attachments: 1. 166022 Change Order #2

Broken Arrow City Council

                                                                                               Meeting of: 05-03-16

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of Minor Change Order C02 for Construction Contract 166022, Central Park Electrical Upgrade

End

Background:

The electrical system at Central Park has proven to be inadequate to support concession and food trailers for large events such as Rooster Days.  As a result, funds were included in a request for Vision 2025 surplus funds to improve the parks electrical system.  The Engineering and Construction Department recommended a contract with the engineering firm of Flynt & Kallenberger, Inc., to upgrade the electrical system.  The design was completed and the project was advertised for bids on November 23 and 30, 2015.  The low bid of $352,596.55 for the base bid and all 14 additive alternates was submitted by and awarded to Third Generation Electrical, Inc.  Notice to Proceed for construction was issued on February 1, 2016.

 

This Change Order addresses the following additions to the contract:

Add into the contract for a metered service to be installed at panel associated with PDU #12.  Removed existing service at PDU #12, include CT can, disconnect, panel board, and halogen light attached. Provide new 400A/1PH/250V, PSO meter and re-feed existing 400A disconnect. This change requires 0 additional contract days.

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $11,130.74

This Change Order:                                                               $1,832.64

Total Cost of Change Orders:                                          $12,963.38

Original Contract Amount:                                          $352,596.55

Revised Contract Amount:                                          $365,559.93

Percent Change in Contract:                                          3.68%


Cost:                                                                $1,832.64

Prepared By:                                           Jeff Bigby, P.E, Acting Director of Engineering and Construction

Reviewed By:                                          Engineering and Construction Department                                  
                                    Finance Department
                                    Assistant City Manager - Operations
                                    Legal Department
                                 

Approved By:                      Michael L. Spurgeon, City Manager

                

Attachments:                                          Minor Change Order CO2

Recommendation:

Approve Minor Change Order C02 in the amount of $1,832.64 for electrical upgrades.