Title: Approval of and authorization to execute an Agreement for Professional Consultant Services (Architect-Engineer agreement) for conceptual design of 23rd Street from New Orleans Street to Houston Street, a Surface Transportation Program Project
Attachments: 1. 151109 AE Agreement 23rd New Orleans to Houston

Broken Arrow City Council

                                                                                               Meeting of: 11-09-2015

                                                                                    

To:                     Mayor and City Council

From:                     Department of Engineering and Construction

Title: 

title

                     Approval of and authorization to execute an Agreement for Professional Consultant Services (Architect-Engineer agreement) for conceptual design of 23rd Street from New Orleans Street to Houston Street, a Surface Transportation Program Project

End

Background:

The City applied for Federal Fiscal Year (FFY) 2017 and 2018 Federal Highways Administration Surface Transportation Program (STP) funds through the Indian Nations Council of Governments (INCOG) for the preliminary engineering and right-of-way acquisition for widening of 23rd Street (193rd East Avenue, County Line) from New Orleans Street (101st Street South) to Houston Street (81st Street South).  The project is a continuation of the 23rd Street from Houston to Kenosha widening project for which right-of-way is starting.  The federal funds were approved for both years, and subsequently the Oklahoma Department of Transportation (ODOT) advanced the project to start in FFY2015.  In July 2014, ODOT and City staff selected Cowan Group Engineering LLC (CGE) as the engineer, and ODOT has recently completed negotiations with CGE.  The negotiated amount is $327,668.00, and the City’s 25 percent share is $109,222.00.  The Architect-Engineer Agreement is attached.  An ODOT-City Engineering Contract Funding Agreement is a separate agenda item, and payment of the ODOT invoice for the local share is on the claims list. 

 

Staff recommends approval of the Architect-Engineer Agreement with Cowan Group Engineering LLC.  Funding for the City share of the concept design will be from Sales Tax Capital Improvements.


Cost:                                                                $327,668.00 ($109,222.00 City share)

Prepared By:                                           Douglas L. Tiffany, P.E., Director of Engineering and Construction

Reviewed By:                                          Finance Department
                                    Legal Department
                                   Assistant City Manager                           

Approved By:                      Michael L. Spurgeon, City Manager
                                   

Attachments:                                          Architect-Engineer Agreement

Recommendation:

Approve the Agreement for Professional Consultant Services with Cowan Group Engineering LLC, and authorize its execution.